Construction measure | Extension and modernisation of the higher social court building |
Completion | 2010 |
Investment | 5,2 Mio. € |
Area | Net area of old structure approx. 3,018 m² Net area of extension approx. 978 m² |
Client | Saarland |
Execution | Project management LEG Saar |
This building with its impressive fire safety stairs in galvanised steel on Halbergstrasse in Saarbrücken is the modernised and extended building for the Saarland social courts. The court was handed over after a construction period of 22 months. LEG Saar was the service provider for the entire construction measure, commissioned by the state government.