Construction measureExtension and modernisation of the higher social court building
Completion2010
Investment5,2 Mio. €
AreaNet area of old structure approx. 3,018 m²
Net area of extension approx. 978 m²
ClientSaarland
 

Execution

 

Project management LEG Saar
SiGeKo (health and safety) through LEG Service

 

This building with its impressive fire safety stairs in galvanised steel on Halbergstrasse in Saarbrücken is the modernised and extended building for the Saarland social courts. The court was handed over after a construction period of 22 months. LEG Saar was the service provider for the entire construction measure, commissioned by the state government.